top of page
PROJECT SUMMARY

Environmental Construction – Culvert Replacement

Environmental Construction, Special Project
Client:
Confidential - Energy
Year:

2022

Location:
Southern Alberta
Client:
Confidential - Energy
Year:

2022

Location:
Southern Alberta
PROJECT SUMMARY

Environmental Construction – Culvert Replacement

Environmental Construction, Special Project

Resolve Earthworks & Environmental Ltd. was selected as the successful contractor to complete this work through a competitive bidding process. 


The project scope included the following:

  • Due to the smaller diameter and placement of the existing culvert, fish were not able to swim upstream.

  • Multiple parties involved with the pre-planning and execution. Client project team, acquatic consultant, Alberta Environment and The Department of Fisheries and Oceans (D.F.O).

  • Remove existing culvert and replace it with a larger diameter culvert at a lower elevation.

  • Site specific ECO Plan and Health And Safety Plan were developed to ensure construction was completed within the strict site permitting requirements as set out by Alberta Environment and D.F.O.

  • Specialized erosion control measures were implemented to comply with the surface runoff and water management plan for pre and post construction.

  • Fish salvage was completed prior to construction activities.

  • 24hr pump around work area during construction.

  • All work was executed as per design drawing and confirmed in the field via site inspection and survey.

  • Construction was inspected by design engineering firm and Alberta Environment with no recommendations or infractions.

  • Existing road materials were re-used post new culvert installation.

  • To bring local value to the area during the construction, local subcontractors were prequalified and utilized when available.

Resolve Earthworks & Environmental Ltd. was selected as the successful contractor to complete this work through a competitive bidding process. 


The project scope included the following:

  • Due to the smaller diameter and placement of the existing culvert, fish were not able to swim upstream.

  • Multiple parties involved with the pre-planning and execution. Client project team, acquatic consultant, Alberta Environment and The Department of Fisheries and Oceans (D.F.O).

  • Remove existing culvert and replace it with a larger diameter culvert at a lower elevation.

  • Site specific ECO Plan and Health And Safety Plan were developed to ensure construction was completed within the strict site permitting requirements as set out by Alberta Environment and D.F.O.

  • Specialized erosion control measures were implemented to comply with the surface runoff and water management plan for pre and post construction.

  • Fish salvage was completed prior to construction activities.

  • 24hr pump around work area during construction.

  • All work was executed as per design drawing and confirmed in the field via site inspection and survey.

  • Construction was inspected by design engineering firm and Alberta Environment with no recommendations or infractions.

  • Existing road materials were re-used post new culvert installation.

  • To bring local value to the area during the construction, local subcontractors were prequalified and utilized when available.

bottom of page