PROJECT SUMMARY
Environmental Construction – Culvert Replacement
Environmental Construction, Special Project
Client:
Confidential - Energy
Year:
2022
Location:
Southern Alberta
Client:
Confidential - Energy
Year:
2022
Location:
Southern Alberta
PROJECT SUMMARY
Environmental Construction – Culvert Replacement
Environmental Construction, Special Project


Resolve Earthworks & Environmental Ltd. was selected as the successful contractor to complete this work through a competitive bidding process.
The project scope included the following:
Due to the smaller diameter and placement of the existing culvert, fish were not able to swim upstream.
Multiple parties involved with the pre-planning and execution. Client project team, acquatic consultant, Alberta Environment and The Department of Fisheries and Oceans (D.F.O).
Remove existing culvert and replace it with a larger diameter culvert at a lower elevation.
Site specific ECO Plan and Health And Safety Plan were developed to ensure construction was completed within the strict site permitting requirements as set out by Alberta Environment and D.F.O.
Specialized erosion control measures were implemented to comply with the surface runoff and water management plan for pre and post construction.
Fish salvage was completed prior to construction activities.
24hr pump around work area during construction.
All work was executed as per design drawing and confirmed in the field via site inspection and survey.
Construction was inspected by design engineering firm and Alberta Environment with no recommendations or infractions.
Existing road materials were re-used post new culvert installation.
To bring local value to the area during the construction, local subcontractors were prequalified and utilized when available.
Resolve Earthworks & Environmental Ltd. was selected as the successful contractor to complete this work through a competitive bidding process.
The project scope included the following:
Due to the smaller diameter and placement of the existing culvert, fish were not able to swim upstream.
Multiple parties involved with the pre-planning and execution. Client project team, acquatic consultant, Alberta Environment and The Department of Fisheries and Oceans (D.F.O).
Remove existing culvert and replace it with a larger diameter culvert at a lower elevation.
Site specific ECO Plan and Health And Safety Plan were developed to ensure construction was completed within the strict site permitting requirements as set out by Alberta Environment and D.F.O.
Specialized erosion control measures were implemented to comply with the surface runoff and water management plan for pre and post construction.
Fish salvage was completed prior to construction activities.
24hr pump around work area during construction.
All work was executed as per design drawing and confirmed in the field via site inspection and survey.
Construction was inspected by design engineering firm and Alberta Environment with no recommendations or infractions.
Existing road materials were re-used post new culvert installation.
To bring local value to the area during the construction, local subcontractors were prequalified and utilized when available.



